Midway through the PI, a team reports that their committed features are at risk because a critical dependency from another team has not been completed. Both teams raise the issue during the ART Sync, but no agreement is reached. What should the RTE do next?
Technical Program Management Hub
SAFe Practice Question — Scenario-Based
Midway through the PI, a team reports that their committed features are at risk because a critical dependency from another team has not been completed. Both teams raise the issue during the ART Sync, but no agreement is reached.
What should the RTE do next?