Your Challenge:
As an engineering manager, you have a project with four critical tasks to complete. Each task has a different level of importance, and you need to determine the order in which to tackle them.

Here’s what you know:

Task A is important but cannot be started until Task B is completed.
Task C must be done before Task A can start.
Task D can be started at any time but must be completed before Task B can be finished.

Question:
With this information, how should you prioritize the tasks to ensure all dependencies are met and the project is completed efficiently?