At Erachron, we place great importance on education. In addition to our Windows Delay Analysis software, I provide consulting services on delay analysis, planning, and other project management topics. Of course, I also organize training sessions on the topics I perceive to be lacking in the industry and share my training videos through my channel.
#delayanalaysis, #delay, #projectdelay, #windowsdelayanalysis, #schedule,# planning, #management, #projectmanagement, #earnedvalue, #claim, #construction, #project, #
Erachron
Which one is incorrect?
1 year ago | [YT] | 5
View 0 replies
Erachron
What is/are the Right/s of the Contractor When There is Excusable Compensable Delay?
1 year ago | [YT] | 0
View 0 replies
Erachron
What is Excusable Compensable Delay?
1 year ago | [YT] | 1
View 0 replies
Erachron
Which answer is correct?
Activity Duration Predecessor Relation
A 3 - -
B 2 - -
C 5 A SS+1
B FS
D 4 C FF+3
E 8 B SS+1
F 2 C FS
E FS
1 year ago | [YT] | 1
View 0 replies
Erachron
For reinforced concrete work, 10 laborers worked for 15 days, 8 hours per day, and produced 40 m³ of reinforced concrete work. Using this historical data, compute how many days will be required to complete the remaining 1200 m³ of reinforced concrete work with 15 laborers working 8 hours per day.
1 year ago | [YT] | 0
View 0 replies
Erachron
How is the Cost Performance Index (CPI) computed?
1 year ago | [YT] | 1
View 0 replies
Erachron
What is Budgeted Cost of Work Scheduled?
1 year ago | [YT] | 2
View 1 reply
Erachron
What is Earned Value?
1 year ago | [YT] | 15
View 0 replies
Erachron
If we want to use earned man-hour values for disruption analysis for an activity, what is the process for disruption analysis calculation?
1 year ago | [YT] | 0
View 0 replies
Erachron
How Disruption Analysis is Conducted Using Earned Value Analysis When an Activity is Disrupted Solely by Owner's Intervention?
1 year ago | [YT] | 0